The project management was an on-going process, and there has been held 9 meetings in the steering committee and two visits from the monitoring team. The project management has prepared a mid-term report, two progress reports and a technical final report. The executive summaries and the whole technical final report can be seen in “dissemination” or contact AWS for a copy of these reports.

On tour with the Monitoring Team

LIFE Flag at AWS

Status per 2008.09.25