The testing of concrete (from task 6) has finished. The samples were crushed and carbonated and after 28 days the leaching test and analysis of the eluates were performed. The tests showed no significant difference between the leaching from the reference concrete and the concrete with bio ash
Final report for Task 5 is completed.
Status per 2008.09.25